Templates · Area
Packing and dispatch
Manual work at benches only: pick, pack, label. A fifth of orders are urgent with a 2-hour target.
Open it in LinewiseSee pricing
Opens in your browser as a demo copy: nothing to install, nothing saved until you choose.
What is in the model
- Work arriving
- 16 jobs an hour from 08:00 to 15:00, about 112 a day, 5 days a week; 20% urgent
- Equipment
- None: manual work at benches
- Shifts
- Day 08:00–16:00, 4 people
| Task | Minutes | Where | Who |
|---|---|---|---|
| Pick | 6 | Picking shelves | Anyone on shift |
| Pack | 5 | Packing benches | Anyone on shift |
| Label and stage | 2 | Labelling | Anyone on shift |
Every figure can be changed: rename anything, move it on the floor, add tasks, shifts or stations.
Things to try
- Add a person to one shift and compare output, turnaround and cost per job.
- Add a unit of equipment and see whether the extra output pays for it.
- Change the arrival rate to next year’s demand and see where work starts to queue.
- Play the week back and use the heat map to find wasted walking.
Make it yours
Open this template, change it to match your own area, and keep it when it is right.
Other area templates
Testing lab
Samples prepared at a bench, run on six testers, results recorded. Two shifts.
See the template →Filling line
Long automated fill runs on three fillers with setup and cleandown. Three shifts, seven days.
See the template →CNC machining cell
Four machines: load and set, an unattended machining run, unload and deburr, then inspection by a skilled person.
See the template →Heat treatment (batches)
Two ovens that each take eight jobs per load, wait up to an hour for a full load, and need a changeover between loads.
See the template →